Home
Part 2 · Section E

Investment Decisions

Capital budgeting from start to finish: estimating relevant after-tax cash flows, evaluating them with NPV, IRR, payback and the profitability index, and testing how the answer changes under risk. This section is 10% of Part 2 and almost entirely computational.

About 10 of the 100 multiple-choice questions, often with a written-response case. Estimated study time: 18 hours.

0%Section readiness
0 / 3Topics complete
—MCQ accuracy
18 hEstimated study time

Your learning path

Three topics. Get the cash flows right first: most wrong answers come from the cash flows, not the discounting.

0% of topics complete
Topic 1 of 3

Capital budgeting process

The stages of a capital budgeting decision and how to build the three blocks of relevant after-tax cash flow.

The process and relevant cash flowsWhat to include and what to leave out
  1. Identify opportunities linked to strategy; evaluate cash flows and risk; select projects (within any capital limit); implement and monitor; post-audit actual against forecast results.
Relevant and irrelevant cash flows
Include Exclude
Incremental after-tax revenues and cash costs Sunk costs (feasibility studies already paid)
Opportunity costs (a building that could be rented out) Allocated overhead that does not change
Changes in net working capital Financing costs (interest, dividends): the discount rate already reflects them
Cannibalization of existing products' cash flows Depreciation itself (only its tax shield is a cash flow)
Tax effects, including the depreciation tax shield Accounting profit figures without cash adjustment
Exam trapDo not subtract interest from project cash flows. The cost of financing is in the discount rate (WACC); deducting interest as well counts it twice.
Initial investmentCost, installation, working capital, sale of the old asset
Initial investment
$$CF_0 = \text{Cost} + \text{Installation} + \Delta NWC - \text{After-tax proceeds of old asset}$$
After-tax sale proceeds
$$\text{After-tax} = \text{Proceeds} - t(\text{Proceeds} - \text{Book value})$$

A sale below book value produces a tax saving, so after-tax proceeds exceed the sale price.

Exam trapThe tax on selling the old asset is based on the gain over book value, not over its original cost.
Operating and terminal cash flowsThe depreciation tax shield and the end of the project
Annual operating cash flow
$$OCF = (\Delta R - \Delta C)(1 - t) + D \times t$$

D × t is the depreciation tax shield. Equivalent: net income + depreciation (with no financing).

Terminal cash flow
$$CF_{terminal} = \text{After-tax salvage} + \text{Working capital recovered}$$
Exam trapWorking capital recovered at the end is not taxed: it is the return of an investment, not income. Salvage value above book value is taxed.
Instructor noteBuild every capital budgeting answer as a timeline: year 0 outlay, years 1 to n operating flows, and the terminal flows added to year n. Most exam distractors leave out one of the three blocks or tax the wrong item.

Finished Capital budgeting process?

Mark it complete when you can build a full after-tax cash-flow timeline.

Topic 2 of 3

Capital budgeting methods

The five decision rules, how to compute each with tables or formulas, and what to do when NPV and IRR disagree.

NPV, IRR and the profitability indexDiscounted cash-flow methods
Net present value
$$NPV = \sum_{t=1}^{n} \frac{CF_t}{(1 + k)^t} - CF_0$$

Accept if NPV ≥ 0. With even flows: NPV = CF × PVA(k, n) − CF0.

Internal rate of return
$$\sum_{t=0}^{n} \frac{CF_t}{(1 + IRR)^t} = 0$$

Accept if IRR ≥ the hurdle rate. Even flows: the PVA factor at the IRR = CF0 ÷ CF.

Profitability index
$$PI = \frac{PV \text{ of future cash flows}}{CF_0}$$

Accept if PI ≥ 1. Under capital rationing, rank independent projects by PI.

Exam trapUse the PV of an annuity factor only for equal flows starting at year 1. For a terminal flow or uneven flows, use the PV of $1 factor for each year.
Payback and discounted paybackHow fast the investment comes back
Payback period
$$\text{Payback} = \frac{CF_0}{\text{Annual cash flow}} \quad\text{(even flows)}$$

Uneven flows: accumulate until the investment is recovered, then add the fraction of the next year. Discounted payback uses discounted flows.

Exam trapPayback and discounted payback ignore cash flows after the payback point, so a project with large later flows can look worse than it is. Never use payback alone to choose between projects.
NPV vs IRR ranking conflictsTiming, scale and the crossover rate
  • For mutually exclusive projects, NPV and IRR can rank differently when cash-flow timing or project scale differ.
  • NPV assumes reinvestment at the cost of capital; IRR assumes reinvestment at the IRR, which is usually unrealistic. Use NPV.
  • The crossover rate is the discount rate at which the two NPV profiles intersect (the IRR of the difference in cash flows).
  • Non-conventional flows (sign changes more than once) can produce multiple IRRs; modified IRR (MIRR) avoids this.
Exam trapFor mutually exclusive projects, choose the higher NPV, even if the other project has a higher IRR or PI. PI and IRR are relative measures and ignore scale.
Instructor noteWhen the exam says "capital is limited" with independent projects, rank by PI and fill the budget; when it says "mutually exclusive", choose the highest NPV. Those two words decide the method.

Finished Capital budgeting methods?

Mark it complete when you can compute all five measures and resolve an NPV–IRR conflict.

Topic 3 of 3

Risk analysis

Testing how the NPV changes when the forecast is wrong, and valuing the flexibility to change course later.

Sensitivity, scenario and simulationThree ways to model uncertainty
  • Sensitivity analysis changes one input at a time (volume, price, cost, life, discount rate) and shows which matters most; a break-even value is the input level that makes NPV zero.
  • Scenario analysis changes several inputs together (best, base, worst) and weights the NPVs by probability.
  • Monte Carlo simulation draws all uncertain inputs from distributions thousands of times, giving a distribution of NPV and the probability that it is negative.
  • Risk-adjusted discount rate: discount riskier projects at a higher rate than WACC.
Break-even annual cash flow (NPV = 0)
$$CF^{*} = \frac{CF_0}{PVA(k, n)}$$
Exam trapSensitivity analysis changes one variable at a time and ignores correlations and probabilities. A project can survive every single-variable test and still fail in a realistic bad scenario where several inputs move together.
Exam trapAdjust for risk once: either raise the discount rate or use certainty-equivalent (risk-reduced) cash flows, not both.
Real optionsThe value of flexibility
  • Option to expand (follow-on investments if the product succeeds), abandon (sell assets if it fails), delay (wait for information), and flexibility (switch inputs or outputs).
  • Options have value because they let management act on new information; static NPV ignores that, so it can undervalue strategic projects.
  • Option value rises with uncertainty and with the time available to exercise.
Value of a real option
$$\text{Option value} = E(NPV)_{\text{with option}} - E(NPV)_{\text{without}}$$
Exam trapReal options are worth more, not less, when uncertainty is higher: greater uncertainty raises the value of being able to wait, expand or abandon.
Instructor notePost-audits compare actual results with forecasts. They discourage optimistic forecasts (a well-known behavioral bias in capital budgeting) and improve future estimates.

Finished Risk analysis?

Mark it complete when you can compute a break-even cash flow, an expected NPV and the value of a real option.

Calculators

Interactive tools

Each tool is pre-filled with an example from the lessons. Change any input; the results show the method, your numbers and what they mean.

NPV, IRR and payback calculator

Builds the full after-tax cash-flow timeline (initial outlay, operating cash flows with the depreciation tax shield, terminal salvage and working-capital recovery), then evaluates it with every method and draws the NPV profile.

Project data

Print-ready

Formula sheet

Every formula in Investment Decisions, followed by present- and future-value interest tables. Print it from here: the sidebar is hidden and the sheet prints black on white.

Spaced repetition

Flashcards

Recall first, then flip. Your grade schedules the next review (SM-2-lite).

Exam-style questions

Practice MCQs

Practice mode gives instant feedback; timed mode allows 1.8 minutes per question, like the exam. Filter by topic, difficulty, or questions you missed.

Essay section

Written-response practice

Write your answer first (aim for about 30 minutes per case), then compare it with the model answer and score yourself against the rubric. Show your calculations: the exam awards marks for method.

Key terms

Glossary

Search the section's vocabulary. Underlined terms in the lessons show these definitions on hover or keyboard focus.